Cascais Villa

A 1970s villa on the Cascais line, bought by a family who intended to redo the kitchen and were told by us to do the wiring first.

€221,000Contracted and paid

22 weeksOn site

On timeAgainst the contracted date

2025Cascais

Survey to close-out, in the owners' own sequence.

The brief

A 1970s villa on the Cascais line. The family called about a kitchen and were told to do the wiring first.

What the survey found

Every circuit tested on survey day. Nothing outside the two rooms renovated in 2008 had an earth. That single finding turned a kitchen project into a house project.

What we did about it

Full rewire alongside the kitchen, with the option to stage it over two years; they chose to do it once. Sea-elevation windows replaced and the thermal bridge at the slab edge corrected while the wall was open.

“We wanted a kitchen. They showed us the test results and we understood why that was the wrong first move.”

Sofia and Rui T., Cascais

It arrived as a kitchen. The log says otherwise.

Entry one is the circuit test that changed the project. Twenty-two weeks later the house had a new kitchen and, more importantly, an earth.

  1. Day 1

    Survey

    Every circuit tested. None of the sockets outside the two rooms renovated in 2008 had an earth. That changed the project from a kitchen to a house.

  2. Week 2

    Scope

    Full rewire priced alongside the kitchen, with the option to stage it over two years. They chose to do it once.

  3. Week 8

    Envelope

    Windows to the sea elevation replaced, thermal bridge at the slab edge corrected, because the wall was open anyway.

  4. Week 15

    Fit-out

    Kitchen and primary suite delivered as one programme, sharing one plasterer and one tiler rather than two of each.

  5. Week 22

    Close-out

    On date. The energy certificate moved two bands, which was a side effect rather than the brief.

It started as a kitchen and became a house.

Test the circuits before you spend on cabinetry. Ours is a one-day job and it changes what the right project actually is.